Capacity
The Capacity view tracks team availability — PTO and holidays per team member — so your sprint or iteration plan reflects who's actually around.
Team members
Each member’s row shows their availability across the sprint (Scrum) or iteration (Kanban). Gray cells mark days off — PTO or holidays.
PTO management
Click a day cell to toggle PTO. For Scrum teams, PTO days are excluded from capacity calculations; for all teams it gives the team visibility into who’s available when.
Holidays
Holidays show with a special indicator and apply to every team member. Configure them once in Organization Settings and they flow into every team’s capacity.
How capacity is calculated
For Scrum teams:
Available capacity = (Team members × Sprint days) − (Total PTO days) − (Holiday days × Team size)
That figure is what the planning and forecasting views lean on when they reason about how much the team can realistically take on.