Capacity

The Capacity view tracks team availability — PTO and holidays per team member — so your sprint or iteration plan reflects who's actually around.

The Capacity view

Team members

Each member’s row shows their availability across the sprint (Scrum) or iteration (Kanban). Gray cells mark days off — PTO or holidays.

PTO management

Click a day cell to toggle PTO. For Scrum teams, PTO days are excluded from capacity calculations; for all teams it gives the team visibility into who’s available when.

Holidays

Holidays show with a special indicator and apply to every team member. Configure them once in Organization Settings and they flow into every team’s capacity.

How capacity is calculated

For Scrum teams:

Available capacity = (Team members × Sprint days) − (Total PTO days) − (Holiday days × Team size)

That figure is what the planning and forecasting views lean on when they reason about how much the team can realistically take on.